150. The authorization holder must send to the Minister, every Tuesday, the daily reports of the preceding week until the end of the construction work. If the Tuesday is a holiday, the report is sent on the first working day that follows.
O.C. 1253-2018, s. 150.
In force: 2018-09-20
150. The authorization holder must send to the Minister, every Tuesday, the daily reports of the preceding week until the end of the construction work. If the Tuesday is a holiday, the report is sent on the first working day that follows.
O.C. 1253-2018, s. 150.